Home / Projects / Case study

Riverside Residences

Residential, Pune. Two 32-storey towers with a clubhouse and three acres of landscape.

Riverside Residences
Client
Residential developer
Area
11.2 lakh sq ft
Project cost
₹420 Cr
Status
Ongoing, 64% complete

The challenge

The developer had announced possession dates under RERA before the structural design was frozen. Two contractors had already been replaced and the towers were four months behind the launch programme.

What we did

We rebuilt the master programme around the critical path of the core walls, split the finishing work into four packages tendered in parallel, and started weekly look-ahead meetings on site. Every running bill was checked against measured work before certification, and a single cost report replaced three separate spreadsheets.

Results

of delay recovered within the first year
3.5 months
saved on finishing packages through competitive tendering
₹6.2 Cr
RERA possession dates missed so far
0

They told us in month two that the façade package would slip, and what it would cost us if it did. We fixed it in month three.

Director, Projects, residential developer

Planning something similar?

Tell us about your project and we will share how we would approach it.

Discuss your project