- Client
- Residential developer
- Area
- 11.2 lakh sq ft
- Project cost
- ₹420 Cr
- Status
- Ongoing, 64% complete
The challenge
The developer had announced possession dates under RERA before the structural design was frozen. Two contractors had already been replaced and the towers were four months behind the launch programme.
What we did
We rebuilt the master programme around the critical path of the core walls, split the finishing work into four packages tendered in parallel, and started weekly look-ahead meetings on site. Every running bill was checked against measured work before certification, and a single cost report replaced three separate spreadsheets.
Results
- of delay recovered within the first year
- 3.5 months
- saved on finishing packages through competitive tendering
- ₹6.2 Cr
- RERA possession dates missed so far
- 0
They told us in month two that the façade package would slip, and what it would cost us if it did. We fixed it in month three.